Client work: Pronghorn Development

Antelope Data Campus: taking 1.5 GW through county approval in Iron County, Utah

Alpen Systems built the economic and fiscal impact case, led community and stakeholder engagement, and aligned workforce partners for the Antelope Data Campus, which secured its conditional use permit in June 2026.

At a glance

Client
Pronghorn Development
Project
Antelope Data Campus, a 1.5 GW data campus with its own behind-the-meter natural gas power plant
Location
Iron County, Utah
Program value
$30B
Outcome
Conditional use permit secured, June 2026

The challenge

Pronghorn Development set out to take a 1.5 GW data campus, powered by its own on-site natural gas plant, through county approval in rural Iron County. It did so at a time of intense national scrutiny of data centers, when projects that bypassed local decision-makers were meeting public backlash.

What Alpen did

Alpen built the economic and fiscal impact case for the campus, showing the county the jobs, tax revenue and regional benefit at stake. We ran community and stakeholder engagement, and brought in workforce partners including the Utah System of Higher Education (USHE).

Outcome

The campus secured its conditional use permit from Iron County in June 2026. Alpen continues to lead community relations as the project advances.

Why it worked

Antelope was approved by working with county officials rather than around them. Alpen CEO Scott Cuthbertson made that case in The Limits of Top-Down Expansion, published in Data Center POST in July 2026, which contrasts projects pushed through from the top with those, like Antelope, permitted through local government.

See all client work